Coming Soon: On April 2nd, all Suggestion Boxes will be migrating to The Network, Trimble's online user community. Your posts, votes, comments, and user accounts will transfer. This site will become read-only after the migration, and this banner will have a link to the new location for ProjectSight suggestions.
Created by Mercedes Green
Created on Oct 5, 2023

There needs to be a PO and Subcontract Cost Release Procedure

Before moving to ProjectSight, if a PO was estimated to be $100,000 but due to timing, schedules, etc we only get invoiced $75,000, we need a way to release the remaining $25,000 as it will never be invoiced. The same could hold true for a Subcontract, but we could always do a change order to fix those.

POs for large concrete orders, or rentals, or blanket POs, we can never really estimate the real total.


Now our commitments are off. In Vista, we can use the PO Close feature will look at invoiced to date and if we choose to close it, the remaining costs are posted as negatives in job cost so total commitment shows $75,000 and current PO amount is $75,000.

  • Attach files
  • Mercedes Green
    Aug 13, 2025

    This has caused many issues between our site teams and finance showing the wrong commitments on reports. Is this being considered for all the Vista customers?