Skip to Main Content
Welcome to the ProjectSight Idea Portal

Your feedback is an essential part of how we continually improve ProjectSight. You can use this page to submit new ideas, or vote on ideas from other users.

This portal is for suggesting enhancements only. If you are experiencing a product defect, please contact support.

ADD A NEW IDEA

All ideas

Showing 2279

Add zoom tools to drawings and drawing sets

Similar to the specification view tools, the drawings and drawing sets would benefit from added zoom tools to control the page view. Manual Zoom, Marquee Zoom, etc.
Jennefer Waskul about 1 year ago in PS Web App & Platform / Drawings 0

Include the ability to add Custom fields to all tabs.

When adding custom fields a limited number of tab choices are available. it would be nice to be able to add custom fields to any form tab.
Trimble ProX Team over 5 years ago in PS Web App & Platform / Custom Fields 0

Drawings Tab needs to be collapsible

A recent update added a drawings tab to the left side of the drawing viewer to quick select drawings without needing to go back a page to select a new drawing. Unfortunately, the new tab menu is not collapsible, so you cannot see around 1/3 of the...
Nick West 7 months ago in PS Web App & Platform / Drawings 0

Could we change the Cost Period Current Period setting to fall over the current date? Please

Clients in support typically ask about this. They do not want to have to keep going to set the Current Cost Period in the Settings and to make matters worse we force them to set it per project (Existing idea for Portfolio setting current period: h...
William Atchison over 1 year ago in PS Web App & Platform / Budget & Cost Management 0

Cost to Complete

Please allow a new budget column to be added as well as a budget header for Cost to Complete. Cost to complete = Total Committed Cost - Actual Cost to date. Can the cost to complete come from commitments and not the budget?
Henrick Malpica over 1 year ago in PS Web App & Platform / Budget & Cost Management 1

Track aging of RFI's on log. Create calendar day count between date created and current date. Add this to the log.

To keep track of the duration that an RFI has been opened. This is good data to report to the Architect and Owner.
Guest over 2 years ago in PS Web App & Platform / Document Control 1

Bulk Remove Users from a project

Please allow the ability to batch edit user access on the project level. For example, if I need to remove 30 users from accessing a project. I would checkbox each user's name and then remove them all from one project at once.
Henrick Malpica over 2 years ago in PS Web App & Platform / Project Directory 0

Daily Safety Inspections

my job is required to have trade partners complete pre-start scissor liftequipment inspections. This in turn requires my team to print off over 100 inspection sheets per week and then attempting to scan them in to our point file. If there was a wa...
Jace Mott about 1 year ago in PS Mobile Apps / Checklist 0 Future consideration

When Adding a Submittal in the "Enter a Description Box" the Option is to Add a Link & Upload a File

Until the Submittal is saved as a Draft the option to add a "DOCUMENTS FOR REVIEW" is not available. This leads to confusion, maybe the "Add a Link" should not be present or the Document for Review option in should be available in some format.
Brian Shawe over 5 years ago in PS Web App & Platform / Document Control 0 Future consideration

OwnerContract Integration - Flow from PS to Spectrum

I know the Owner contract integration is planned. It appears to be flowing from Spectrum to PS. It would be much better to flow from PS to Spectrum. PS is much more user-friendly. This information flows from the project manager to accounting. The ...
Nancy Burriss about 1 year ago in PS Web App & Platform / Integrations 0