Coming Soon: On April 2nd, all Suggestion Boxes will be migrating to The Network, Trimble's online user community. Your posts, votes, comments, and user accounts will transfer. This site will become read-only after the migration, and this banner will have a link to the new location for ProjectSight suggestions.
Created by Pooya Akram
Created on Nov 28, 2023

The final substantial completion date does not add up with the original substantial and additional change order days

Hi,

when the change orders add a number of days to the project, it means working days not calendar days but (as you can see in the attached pictures from one of our projects) in the Prime Contract detail, Project Sight does not exclude the weekends and holidays from those days and just adds up all approved change order extra days with the original substantial date.

Can you please fix that?