Coming Soon: On April 2nd, all Suggestion Boxes will be migrating to The Network, Trimble's online user community. Your posts, votes, comments, and user accounts will transfer. This site will become read-only after the migration, and this banner will have a link to the new location for ProjectSight suggestions.
Categories Forms
Created by Guest
Created on Jan 27, 2025

"Pending" Subcontractor Change Orders

  • Regarding the “pending” subcontractor change orders, as of right now, when you create the change order to the subcontractor, it automatically moves it from the pending column to the approved commitments on the Financial Status Report. Ideally, the subcontractor change order shouldn’t move to the approved commitments until it’s been executed by both parties.

  • Attach files
  • Mercedes Green
    Mar 14, 2025

    This has also caused some confusion and affects our forecasting. We may be sitting on a lot of SubCOs that the owner or trades have not yet signed, so they are technically not approved. It would be helpful if the "Allocation Types" are brought over to the SubCO so we manually change to Appr Commit and that would then change it on the PCO it's linked to.